Two drops.
Two outcomes.

The shallower drop in this pair has the higher-rated turbine. Head is one part of the site assessment.

Compare the published figures
1.2 m

Morden Hall Park

2.4 m

Dandridge’s Mill

Illustrative sections on a common vertical scale

Compare the schemes

Head is the difference in water levels. Rated power is measured in kW and annual generation in kWh.

MeasureMorden Hall ParkDandridge’s Mill
Head1.2 m2.4 m
FlowUnpublished0.36 m³/s
Rated power8.5 kW5 kW
Annual generationUnpublishedOver 27,000 kWh
A covered screw turbine runs down the bank alongside a stepped spillway.
Screw turbine and spillwayCragside · illustrative stock photograph
Image credit

“Tumbleton Lake spillway and Archimedes Screw power plant, Cragside Estate, Rothbury, England” by Rosser1954 on Wikimedia Commons. Resized, converted to WebP and displayed cropped. Photograph and adaptation licensed under CC BY-SA 4.0 (creativecommons.org/licenses/by-sa/4.0/). Source commons.wikimedia.org/?curid=52453932.

Morden Hall Park

National Trust

The 8.5 kW Archimedes screw supplies the stable yard visitor centre and Snuff Mill. Hallidays describes it as London’s first hydroelectric turbine.

Dandridge’s Mill

East Hanney, Oxfordshire

The Grade II listed former silk mill was restored as four low-energy homes. Hallidays designed, installed and operated its 5 kW Archimedean HydroScrew. The case study describes it as the UK’s first domestic hydropower screw installation and reports over 27,000 kWh a year for electricity and heating.